Renovations
Fallowfield HMO Renovation
Two side by side 2 bedroom properties owned by the same client, converted each into 6 bed HMO investment properties with three bathrooms each.
Location: Fallowfield, M14
Duration: 12 weeks for both properties
Scope: Timber frame, slate, steel, woodwork, cladding, carpet flooring, tiling, electrics, new plumbing.
Stockport Road Extension
Large development with side and rear extension, dormer conversion, internal reconfiguration and rear garden office.
Location: Altrincham, WA14
Duration: 22 WEEKS
Scope: Groundworks, brick and blockwork, steelwork, bi-folding doors, tiling, dormer roofing, bathroom, electrics re-wiring, garden and landscaping, rear garden office and store.
-
Completed Extension Exterior
-
Completed Extension Interior
-
During Build
-
During Build
-
During Build
-
During Build
Weldon Road Renovation
2 bedroom Family home extended to create 3 double bedrooms and a large bathroom. Full loft conversion by dropping ceilings. Re-plastered, full electrical re-wire and new boiler along with small knock through inside kitchen.
Location: Weldon Road, Altrincham, WA14
Duration: 12 weeks
Scope: Rip out and new ceilings, velux windows, new bathroom and kitchen.
-
Completed Interior
-
Completed Interior
-
Completed Interior
-
Completed Interior
-
Completed Interior
-
Completed Interior
-
Completed Interior
-
Completed Interior
-
During Build
-
During Build
-
During Build
-
During Build
Hale Renovation
Large development with front and double side extension.
Location: Hale, WA13
Duration: 16 weeks
Scope: Brick and blockwork, steelwork, bifolding doors, engineered wood flooring, exterior rendering to match existing, exterior porch lighting.
-
Completed Exterior
-
Completed Interior
-
Completed Interior
-
Completed Interior
-
Completed Interior
-
Completed Interior
-
Completed Exterior
-
During Build
-
Before Renovation
Pickmere Renovation
4 bed family home that underwent several projects including a dormer, garage conversion and two bathrooms along with extensive electrical work and redecoration.
Location: Pickmere, CW9
Duration: 12 weeks
Scope: New openings, timber work, insulation, floors, electrics, stud work and decorations.
-
Completed Exterior
-
Completed Interior
-
Completed Interior
-
Completed Interior
-
Completed Interior
-
Completed Interior
-
Completed Interior
-
Completed Interior
-
Completed Interior
-
Completed Exterior
-
Completed Interior
-
Completed Interior
-
During Build
-
During Build
-
Before Renovation
-
Before Renovation
Didsbury Renovation
Large 6 bedroom family home with added floors and multiple extensions.
Location: Didsbury, M20
Duration: 4 weeks
Scope: Stud work, plastering and joinery works.
-
During Build
-
During Build
-
During Build
-
-
During Build
-
During Build
-
During Build
-
During Build
-
During Build
-
During Build
Bowden Renovation
Large family home with roofing works, exterior rendering and groundworks.
Location: Bowden, Cheshire, WA14
Duration: 4 weeks
Scope: Roofing works, rendering, joinery, new fencing, timber decking, groundworks.